Cope Construction
is undertaking the civil site works as part of the large
Co-Generation plant currently under construction in
Sarnia. The project required that a 48” diameter
cooling water outflow be connected to the existing 96’diameter
sewer.
The location for the connection was constrained by various
site issues and had to be made at an intersection with
several existing underground services. The coffer dam
was bounded on all four sides by existing services.
Three large diameter pipes (96”, 78”
and 48” had to be maintained through the coffer
dam at different elevations. The
contractor also had to excavate to approximately 9 metres
below grade outside
of one wall of the cofferdam at one point during the
installation.
Riggs Engineering designed a system incorporating steel
sheet piles and H-piles with timber lagging to facilitate
the existing piping. Active earth pressures were calculated
using Rankine theory. Passive soil pressures were calculated
using the modulus of sub-grade reaction. We carried
out finite element analyses of the various stages of
excavation and backfilling and designed all of the structural
elements and connections.
The location of struts and reinforcing elements were
selected in close consultation with the contractor to
accommodate their concrete forming needs and to allow
for excavation to
the specified depths.
|