In the
summer of 2000 Riggs Engineering carried out a preliminary
investigation of the concrete west breakwater at Erieau.
The level of funding was established by PWGSC’s
client department at $750,000 and we proceeded with
detailed design. Philip Lampkin was the lead design
engineer while some design development and quality assurance
was carried out by Brian Riggs. During the design development
we became aware of
the current favourable tendering environment for contractors.
At the same time the client
department wanted a more comprehensive repair program
than initially envisioned.
An exhaustive review of the specification was completed
to identify any items that could raise costs beyond
the project budget. The site was once again reviewed
with a geotechnical engineer and final changes were
made to the tender documents.
Tenders closed on budget and a contract was awarded
with a completion target of December 2000. The project
had detailed forming and concrete placement requirements.
Because of the project complexity Philip Lampkin was
on site full time for the initial two months of the
project. The contractor proposed overbuilding the width
of the structure to allow vehicle access over the full
length of the structure. While the concept was sound
he had not fully developed all the consequences of such
a construction method. He attempted to develop his methods
and details “on the fly”. Mr. Lampkin’s
presence on-site ensured sound engineering decisions
were made in a timely fashion to ensure project success.
The early on set of winter was preceded by a very windy
month of November and the contractor was not able to
complete the work within the specified time of completion.
Riggs Engineering worked closely with the contractor
to refine methods and to determine adequate weather
protection that would allow the project to proceed in
winter conditions. Mr Dean Denniss very ably replaced
Mr. Lampkin on site and the contractor proceeded to
place over 300 cubic metres of concrete during a severe
winter. |