Lavis Construction
Co. Ltd. received a $1,100,000 contract from the Ministry
of Transportation of Ontario for the rehabilitation
of the Highway 21 bridge at Bayfield. The project included
a complete replacement of the gabion retaining structures
in the river with steel sheet piling. To facilitate
removal of the gabions and to enhance the slope stability
of the existing bank, which is at a slope of 1.6 to
1, we proposed a temporary berm be constructed in the
river and expedited regulatory approval. This enabled
the contractor to significantly reduce the amount of
work that had to be carried out from floating plant.
Philip Lampkin was the quality verification engineer
for the installation of the soil anchors. This involved
proof testing of the one tie rod to specified loads
and measuring deflection over a period of time. We analysed
the results to provide a determination of the working
load capacity of the tie rods. The test results established
the acceptablity of the anchor
construction and strength. The remaining production
anchors were subsequently tested to specified acceptance
criteria.
The contract also required that the wales of the new
wall be curved to follow the 10 metre radius of the
proposed alignment. The wales could not be bent, however,
because they were specified to be inclined to the wall
to accommodate the specified slope on the soil anchors.
This was a mistake in the contract and Riggs Engineering
was asked to provide a solution. We undertook a finite
element analysis of the structure and determined the
complete stress distribution along the wales. We proposed
that the wale channels be cut in 1.22 metre sections
to match the profile of the steel sheet piles. We designed
a combination of partial penetration groove welds, flange
plates and web plates to fully transfer the shear, axial
and bending stresses in the connections. We provided
detailed
shop drawings and design calculations for approval by
MTO. The work was successfully implemented by the contractor.
|